Volume 2, Issue 3 (7-2012)                   IJOCE 2012, 2(3): 341-355 | Back to browse issues page

XML Print


Download citation:
BibTeX | RIS | EndNote | Medlars | ProCite | Reference Manager | RefWorks
Send citation to:

Csébfalvi A. A UNIFIED MODEL FOR RESOURCE-CONSTRAINED PROJECT SCHEDULING PROBLEM WITH UNCERTAIN ACTIVITY DURATIONS. IJOCE 2012; 2 (3) :341-355
URL: http://ijoce.iust.ac.ir/article-1-95-en.html
Abstract:   (17162 Views)
In this paper we present a unified (probabilistic/possibilistic) model for resource-constrained project scheduling problem (RCPSP) with uncertain activity durations and a concept of a heuristic approach connected to the theoretical model. It is shown that the uncertainty management can be built into any heuristic algorithm developed to solve RCPSP with deterministic activity durations. The essence and viability of our unified model are illustrated by fuzzy examples presented in the recent fuzzy RCPSP literature.
Full-Text [PDF 152 kb]   (6426 Downloads)    
Type of Study: Research | Subject: Optimal design
Received: 2012/08/3 | Published: 2012/07/15

Add your comments about this article : Your username or Email:
CAPTCHA

Rights and permissions
Creative Commons License This work is licensed under a Creative Commons Attribution-NonCommercial 4.0 International License.

© 2024 CC BY-NC 4.0 | Iran University of Science & Technology

Designed & Developed by : Yektaweb