Volume 3, Issue 4 (10-2013)                   IJOCE 2013, 3(4): 543-561 | Back to browse issues page

XML Print


Download citation:
BibTeX | RIS | EndNote | Medlars | ProCite | Reference Manager | RefWorks
Send citation to:

Danka S. ROBUST RESOURCE-CONSTRAINED PROJECT SCHEDULING WITH UNCERTAIN-BUT-BOUNDED ACTIVITY DURATIONS AND CASH FLOWS II. SOUNDS OF SILENCE: A NEW SAMPLING-BASED HYBRID PRIMARY-SECONDARY CRITERIA HARMONY SEARCH METAHEURISTIC . IJOCE 2013; 3 (4) :543-561
URL: http://ijoce.iust.ac.ir/article-1-150-en.html
Abstract:   (16757 Views)
In this paper, we present a new idea for robust project scheduling combined with a cost-oriented uncertainty investigation. The result of the new approach is a makespan minimal robust proactive schedule, which is immune against the uncertainties in the activity durations and which can be evaluated from a cost-oriented point of view on the set of the uncertain-but-bounded duration and cost parameters using a sampling-based approximation. In this paper, we assume that the sources of uncertainty are the variability of the activity durations and the cash flow values, and present an appropriate hybrid method, which is a combination of mathematical programming, metaheuristic and sampling-based elements, to cope with this "uncertainty in uncertainty" like real problem.
Full-Text [PDF 176 kb]   (5816 Downloads)    
Type of Study: Research | Subject: Optimal design
Received: 2013/10/12 | Accepted: 2013/11/19 | Published: 2013/11/19

Add your comments about this article : Your username or Email:
CAPTCHA

Rights and permissions
Creative Commons License This work is licensed under a Creative Commons Attribution-NonCommercial 4.0 International License.

© 2024 CC BY-NC 4.0 | Iran University of Science & Technology

Designed & Developed by : Yektaweb